WARSAK
DAM
KEY FACTS
| Dam
Type: |
Concrete
Gravity |
| Height: |
250
ft. (maximum above river bed) |
| Catchment
Area: |
26,000
sq. miles |
| Design
Flood Discharge: |
540,000
cusecs |
| Total
Storage Capacity: |
76,510
million m3 |
| Live
Storage Capacity: |
31,210 million m3 |
| Year
of Completion: |
1960 |
| Geology
and Bedrock: |
Granite
and Schist |
| Length
of Spillway: |
460
feet |
| No.
of Bays: |
9 |
| Height
of Bay: |
40
feet |
| Total
Volume of Dam: |
42,000
yds3 |
| Power
Generation Capacity: |
240
MW (6 x 40 MW) |
| Capacity
of Irrigation Tunnel: |
3.5
miles, 10-ft. diameter and 500 cusecs discharge |
| |
LOCATION
OF THE DAM
The
Warsak Dam is located on the Kabul River in the province of NWFP,
Pakistan, about 19 miles northwest of the city of Peshawar. The
river rises in Afghanistan and provides drainage for the eastern
part of that country. From Kabul, it flows eastwards through Jalalabad
valley to the border between Afghanistan and Pakistan.
In
Afghanistan, the River Kabul receives four large tributaries i.e.
Logar, Panjshir, Alingar and Kunar. The catchment area of the river
is about 26,000 sq. miles of which the Kunar valley alone contributes
9,500 sq. miles - most of which lies in Pakistan. The Kabul River
falls into the mighty Indus near Attock, about 50 miles from Warsak
dam.
ALTERNATIVE
DAM SITES
Seven
dam sites were considered for the siting of the dam. These were
located 2-4 miles upstream of the Warsak head canal. Topographically,
the most suitable sites for the dam were the three most upstream
where the gorge was narrow and banks steep but these required larger
amount of tunneling and the rock quality in this part was of inferior
quality compared to the other sites downstream. The first site,
the most downstream of the seven had best rock quality but a very
wide gorge which would have increased the cost of the project immensely.
Between the remaining three sites, one had poor geological conditions
were not acceptable. Construction work started at dam site 2 in
February 1949 but due to cracked rock findings the work was shifted
to the 4th site from the head canal where rock quality was good
and the gorge was not too wide.
PROJECT
EXECUTION
The
Warsak Multipurpose Dam was the first initiative of its kind after
independence in Pakistan. The Government of Pakistan and the Government
of Canada jointly executed the gigantic undertaking. The project
took 5 years for completion through aid under the Colombo Plan by
the Canadian government, setting a milestone of collaboration between
the Commonwealth countries. The original estimated cost of the project
by PC-1 in 1955 was Rs. 15.6 crores (Rs. 156 million).
Initially,
the Government of Pakistan entrusted the then Central Engineering
Authority (CEA) to carry out investigations for the project. Later,
in December 1948, local consultants M/s Merz, Randell, Vetten (Pakistan)
initiated investigations to estimate the cost. The Canadian consultants
for construction were H.G. Acres and contractors were Angus Robertson
Ltd. Pakistani counterparts were deputed from the CEA.
COMPONENTS
OF THE DAM
The
area termed as the Warsak dam site includes the main dam, stilling
basin, powerhouse, power tunnel with penstocks and the diversion
tunnel. All structures are located close to each other and the rock
units are similar. Generally, the rock units may be divided into
four categories (i) lower granite gneiss, (ii) multiple schist band,
(iii) upper granite gneiss, and (iv) the phyllite - schist group.
The
Warsak dam is a concrete, straight gravity type bulkhead. It is
460 feet high along the crest with a maximum height above the lowest
bed rock foundation level of 220 feet. The spillway has been incorporated
as an overall structure of the dam that consists of nine bays; each
having high gates of 40 feet. Below the dam, a concrete stilling
basin is provided to absorb and dissipate the energy of the falling
floodwaters.
The
powerhouse is located on the surface, on the right bank below the
downstream face of the dam. A 35 feet internal diameter tunnel,
which is 1,800 feet long with a maximum discharging capacity of
32,500 cusecs, is located along the left bank of the river extending
from upstream to downstream face of cofferdam. Two cableway benches
for concrete bucketing for the dam and stilling basin are also provided
along the hill-slopes. The intake structure and power tunnel, having
an internal diameter of 39 feet, are located on the right bank.
There are 6 underground penstocks with 18 feet diameters for the
6 generators. A 3.5 miles long, 10 feet diameter concrete lined
irrigation tunnel is located on the right bank to irrigate 120,000
acres of land.
CURRENT
STATUS
There
was no provision of silt exclusion in the design of Warsak dam,
which resulted in silting up of the reservoir after three years
of operation of the dam. Currently, the riverbed on the upstream
side of Warsak dam has been raised to the extent that the dam is
essentially run-of-the-river, with no capacity for storage.
Hydroelectric
power is still produced but silting-up is a persistent problem for
the power generators due to the inflow of coarse sediment. The Federal
Government has allocated Rs. 77 million for the rehabilitation of
Warsak Dam in 2001-02.
RECENT
INTERVENTIONS
Since
its commissioning in 1960, the condition of the power station has
been deteriorating. This is mainly due to structural deformations,
sedimentation problems and erosion in hydraulic equipment. The power
station has been rehabilitated under a CIDA grant to restore its
rated capacity and to enhance its operational life and reliability
for 20-25 years.
At
present, the overhauling of two units has been completed. As a result
of this, the generation of power has increased. There was a 24.4
% increase in power generation in the year 2000 compared to the
past year.
The
Dams Safety Organization has been conducting annual inspections
of Warsak Dam. This includes piezometric analysis and evaluation,
collection of updated seepage and movement data of project structures.
The findings and recommendations are issued bi-annually.
REFERENCES
1.
Warsak Dam Organization, "Warsak Dam Multi-purpose Project
- Completion Report".
2. Dr. Nazir Ahmed, "Water Resources of Pakistan"' Mirajuddin
Press, Lahore, September 1993.
3. Pakistan Water and Power Development Authority, "Annual
Report 1999-2000", 2001.
4. Pakistan Water & Power Development Authority, "Monthly
Progress Report for February 2002", Hydroelectric Planning
Organization, March 2002.
|