|
HYDEL
POWER POLICY - 1995
INTRODUCTION
In
Pakistan, nearly all the hydropower potential results from discharges
into the Indus River Basin. These discharges result primarily from
precipitation and snowmelt in the northern mountainous ranges of
the country. They occur in small rivulets that flow down to the
larger tributaries of the river Indus and finally converge into
the mighty Indus itself.
Hydropower
is characterized by two major constraints: the remote location of
the power plants and the seasonal variations in river discharges,
which are of a relatively greater proportion compared to most other
countries, due to extreme climatic and precipitation conditions
in Pakistan.
PRIVATE
POWER POLICIES
The
following policies have been announced in Pakistan since 1994:
-
Policy
Framework and Package of Incentives for Private Sector Power
Generation Projects in Pakistan, March 1994.
-
Policy
Framework and Package of Incentives for Private Sector Hydel
Power Generation Projects in Pakistan, May 1995.
-
Policy
for New Private Independent Power Projects, July 1998.
THE
NEED FOR A HYDRO POWER POLICY
Hydropower
development is the need of the time for the following reasons:
1.
to meet future power shortages which will start affecting the national
economy from the year 2004-2005
2. to improve the thermal-hydro mix from 75:25 ratio in order to
produce cheaper energy which is essential for a developing country
like Pakistan
3. to utilize a renewable resource indigenous to the country rather
than importing expensive fuels
There
has been a period of dormancy in hydropower development since the
construction of Tarbela Dam project in 1976. A Hydropower Policy
is necessary to evoke response from the private sector and to bridge
the gap in hydropower development. In view of the urgency and multitudinous
constraints i.e. remote location and seasonal variations associated
with the development of hydropower plants, the Government has devised
an attractive policy package to promote interest towards their development.
POWER
INDUSTRY IN PAKISTAN
The
power industry in Pakistan primarily consists of two Government-controlled
utilities, the Water and Power Development Authority (WAPDA) and
the Karachi Electric Supply Corporation (KESC) with an increasing
role of the private sector. These two utilities operate independently
except for one 220 KV double circuit and two 132 KV links between
them which each utility operates as a separate island. Together
the two utilities are responsible for power generation, transmission
and distribution to approximately 13.3 million consumers in the
country. The Ministry of Water and Power controls both WAPDA and
KESC. Approximately 95% of the grid system is operated by WAPDA
and the balance by KESC.
In
addition to the national grid, several Independent Power Producers
(IPPs) are also operating to meet national power needs.
GROWTH
PATTERN OF INSTALLED CAPACITY
The
total installed capacity in the country at the time of independence
was 50 MW. In 1958, when WAPDA was constituted, the installed capacity
was 174 MW, of which 119 MW was in the area where WAPDA operates
and 55 MW in the areas where KESC operates now. The decade-wise
increase in the installed national capacity since 1947 excluding
the nuclear power plants is as under:

NOTE:
A. With the addition of CHASNUPP`s 325 MW to the KANNUP's earlier
137 MW, Pakistan's total installed nuclear power capacity is 462
MW.
B.
The installed capacity of the WAPDA system decreased during the
year 1999-2000 because the following plants were removed from the
system due to poor efficiencies:
1. Mesco 20 MW
2. Shahadra 85 MW
The following plants were derated:
1. Multan derated to 195 MW from 260 MW
2- Quetta 3-6 derated to 42 MW from 85 MW
C.
The 50 MW Sukker power plant was been taken out of the system during
the year 2000-2001 and the following plants have been derated:
1. Jamshoro derated to 850 MW from 880 MW
2. Muzaffargarh derated to 1350 MW from 1370 MW
HYDEL
POWER POLICY -1995
After
the success of 1994 Power Policy, the Government announced the Hydel
Power Policy in May 1995 called "Policy Framework and Package
of Incentives for Private Sector Power Generation Projects in Pakistan".
The salient features of this policy are:
-
Choice
of Site and Equipment
Investors are free to propose hydel power plants on tributaries
and canal systems at any location and opt for any type of equipment.
However, seasonal storage plants are only allowed on streams
and tributaries.
The policy covers all feasible hydropower plants up to 300 MW.
Rivers are excluded but plants with capacities more than 300
MW which do not disturb the downstream user's water rights and
do not undermine the optimum development potential of a site
would be considered on case to case basis.
-
Feasibility
Studies
The private sector should carry out feasibility studies at their
own expense to discern technical and economic feasibility and
evaluate if the plant factor is > 50%, 40% energy is produced
during low-water months (January - June), etc.
-
Financing
Arrangements
The Government will raise funds without any direct sovereign
guarantee of repayment; therefore, investors/ lenders should
look forward to revenues by the sale of electricity.
The minimum requirement for equity investment is 20% of the
total capital cost of the project.
Up to 30% of the capital cost of the project may be provided
through a Private Sector Energy Development Fund (PSEDF) with
a variable interest rate and maturity period up to 23 years
including a grace period of 8 years.
Power generation companies may issue corporate bonds or shares
at discounted price. Moreover, foreign banks may underwrite
the issuance of shares. A tax facility similar to non-banking
financing institutions, 80:20 debt equity ratio, abolition of
5% limit on investment of equity are also extended.
-
Net
Profits
Article 16(2) of the Constitution of Pakistan regarding profits
from hydropower generation is not applicable to the private
sector. However, a nominal price for the use of water as Bulk
Power Tariff at a rate of 0.233 US cents/ Kwh should be paid
to the provincial governments.
-
Fiscal
Incentives
The private power generation companies are exempt from corporate
income tax, sales tax/ Iqra/ flood relief and other surcharges
on the import of all types equipment for generation/ transmission/
distribution with the exception of 2% custom duty on imported
machinery.
Repatriation of equity along with dividends is allowed freely.
Exemption from income tax in Pakistan to foreign lenders to
such companies.
Private power companies may get insurance from any source and
will also be eligible for other concessions given to industrial
projects.
-
Security
Package
Model Implementation and Power Purchase Agreements have been
prepared to eliminate the need for protracted negotiations between
the Government and Sponsors.
The ownership of the project will be transferred to the Government
free of charge after 25 years of its operation.
The Government will provide protection against specific force,
major risk, and protection against changes in certain taxes
and duties and ensure convertibility of rupee and remitability
of foreign exchange.
-
Application
and Processing
Letter of Interest and Letter of Support will be dealt by provincial
Governments.
Registration of applicant and application form is given by provincial
Private Power Cells for Rs. 5,000/-. Whereas, applications will
be accepted against a non-refundable fee ranging between Rs.
30,000-500,000 for power plants between 0-300 MW and larger.
The Government will charge the price of the feasibility study
if it has been completed in the public sector.
-
Tariff
for Bulk Purchase of Power
A Bulk Power Tariff applies according to the following:
| Capacity |
Rate
US
Cents/ Kwh
|
Timeframe |
| Upto
20 MW |
6.1 |
For
first 10 years |
| Upto
20 MW |
5.57 |
Levelized
for the first 25 years |
| 21-300
MW |
6.0 |
For
first 10 years |
| 21-300
MW |
4.7 |
Levelized
for the first 25 years |
| 300
MW and above |
|
Case
to case basis |
The
Bulk Power Tariff has been calculated on an annual plant factor
of 50%. The payment will be made on the basis of actual energy sold
to WAPDA on a monthly basis. WAPDA will deduct US cents 0.233/ Kwh
as price of water.
-
Indexation
/ Adjustment
The base price for use of water will be paid in equivalent rupees.
The variable O&M cost is directly escable from financial
close against exchange variations of Pak Rupee to US Dollar
and US inflation rate as determined by State Bank of Pakistan
and Consumer Price Index.
-
Environmental
Study
Every proposal for private power company will be liable to conduct
an Environmental Impact Assessment as applicable by statutory
requirements by the Pakistan Environmental Protection Laws and
should be in accordance with the EIA Guidelines issued by the
Ministry of Environment, Local Government and Rural Development.
SALIENT
FEATURES OF 1998 POLICY FOR NEW PRIVATE IPPs
-
The
total power demand in Pakistan was estimated to range between
19,000 MW and 25,500 MW by July 2008.
-
The
existing generating units and committed additions to capacity
in both the public and private sector were expected to meet
the demand until the year 2002-2003.
-
The
shortfall in generating capacity was expected to range between
5,000 MW and 8,500 MW until July 2008, based on population trends
and hydrologic variations.
-
The
basis for selection of an IPP was a minimum levelized tariff
through International Competitive Bidding (ICB). The process
of selection involved pre-qualification, issuance of a Request
For Proposals (RFP), bidding and evaluation of bids against
bid criteria clearly laid out in the RFP.
-
Detailed
feasibility studies were required before the bids were to be
invited.
-
Hydropower
projects were to be implemented on Build-Own-Operate-Transfer
(BOOT) basis.
-
Initially
projects based on hydro and indigenous coal were to be entertained.
-
No
blanket exemptions from duties and taxes were provided to the
IPPs.
-
Unsolicited
proposals for hydro and indigenous coal based projects were
permitted from sponsors in absence of a feasibility study. The
sponsor was required to complete a detailed project feasibility
study at his own cost and hand over the study to GOP, in order
for GOP to invite bidding. On the conclusion of the bidding
process, the sponsor of the unsolicited proposal were to be
offered the opportunity to undertake the project at the lowest
tariff offered by the bidders. If he rejects this offer, the
successful bidder was required to repay the reasonable cost
of the feasibility study.
-
Adequate
compensation in tariff was provided for projects requiring substantial
investment in dedicated production and / or transportation facilities
for fuel.
DIFFERENCES
FROM 1994 POLICY
After
the announcement of the 1994 Policy Framework and Package of Incentives
for Private Sector Power Generation Projects, thirty-four projects
totaling a net capacity of 9,062 MW were issued a Letter of Support
(LOS). Of these, nineteen projects totaling a net capacity of 3,454
MW achieved financial close.
-
Some
major features more lenient in the 1994 policy are as follows:
-
Bulk
Tariff of US Cents 6.1/kwh was guaranteed for purchase of all
power produced by the IPPs.
-
Freedom
to select technology and fuel was provided to the entrepreneurs.
-
The
IPPs proposed their selected location without any pre-agreed
criteria.
-
Guarantee
of the performance of public sector utilities and fuel supplier
was provided.
-
"One
Window" operation through the PPIB was arranged.
-
Subsidy
on fuel and in the form of other taxes and blanket exemptions
was offered.
WAPDA's
PLAN
A three-phase
Hydropower Development Programme has been prepared by WAPDA as part
of their Vision 2025 philosophy. This development plan was presented
to and approved by the Chief Executive of Pakistan on January 17,
2001.
In
the Vision 2025, WAPDA suggested a plan to meet the upcoming deficits
through additional power generation in three phases i.e short-,
medium- and long-term. Salient features of the plan are:
| |
SHORT
TERM
(2005-06) |
MEDIUM
TERM
(2010) |
LONG
TERM
(2015) |
| Proposed
Capacity Addition (MW) |
715 |
6,497 |
15,887 |
| No.
of Projects |
8 |
Proposed
= 15
Identified
= 9 |
Proposed
= 20
Identified
= 15 |
| Capacity
Addition
Hydro-power
Coal
Gas
Total
(MW) |
715
--
--
715 |
2,897
3,600
--
6,497 |
12,377
2,250
1,260
15,887 |
| Cost
Design/
Documents
Execution |
Rs.
154 M
US$ 0 .77 B |
Rs.
600 M
US$ 7.7 B |
Rs.
1,210 M
US$ 23.84 B |
PROJECTS
IDENTIFIED FOR ADDITION IN CAPACITY
In
accordance with the promotion of the hydropower policy and acknowledging
the necessity for hydropower, WAPDA has identified the following
priority hydropower projects for the short-term, medium-term and
long-term which correspond to 2005-06, 2010 and 2015 respectively.
SHORT
TERM
| Sr.
No |
PROJECT |
CAPACITY (MW) |
YEAR |
STATUS |
| 1 |
Jinnah
(Indus) |
96 |
2005-6 |
Feasibility
Study (F.S) by WAPDA |
| 2 |
Malakand-III |
81 |
2005-6 |
F.S
by Private Sector |
| 3 |
Allai
Khwar |
121 |
2005-6 |
F.S
by Shydo |
| 4 |
Golan
Gol |
106 |
2005-6 |
F.S
by WAPDA |
| 5 |
New
Bong UGC |
97 |
2005-6 |
F.S
by P.S |
| 6 |
Khan
Khwar |
72 |
2005-6 |
F.S
by Shydo |
| 7 |
Duber
Khwar |
130 |
2005-6 |
--do-- |
| 8 |
Pehur
High Level |
12 |
2005-6 |
P.F.S
by WAPDA |
| |
Total |
715 |
|
|
MEDIUM
TERM
| Sr.
No. |
PROJECT |
CAPACITY
(MW) |
| 1 |
Raised
Mangla |
180 |
| 2 |
Thal
Reservoir (CJ Link) |
52 |
| 3 |
Doyian
(NA) |
425 |
| 4 |
Neelam-Jhelum |
969 |
| 5 |
Kohala
(Jhelum) |
740 |
| 6 |
Matiltan
(Ushu) |
84 |
| 7 |
Gulpur
(Punch) |
116 |
| 8 |
Abbasian
(Jhelum) |
245 |
| 9 |
Rajdhani
(Punch) |
86 |
| 10 |
Combined
Cycle on Gas/Coal |
3,600 |
| |
|
|
| |
Total |
6,497 |
LONG
TERM
| Sr.
No. |
PROJECT |
CAPACITY (MW) |
| 1 |
Basha |
3,360 |
| 2 |
Dasu
(Indus) |
2,712 |
| 3 |
Patan
(Indus) |
1,172 |
| 4 |
Thakot
(Indus) |
1,043 |
| 5 |
Bunji
(Indus) |
1,500 |
| 6 |
Munda
(Swat) |
740 |
| 7 |
Chokothi
(Jhelum) |
139 |
| 8 |
Naran
(Kunhar) |
219 |
| 9 |
Suki
Kinari (Kunhar) |
652 |
| 10 |
Patrind
(Kunhar) |
133 |
| 11 |
Azad
Patan (Jhelum) |
222 |
| 12 |
Karot
(Jhelum) |
240 |
| 13 |
Mahl
(Jhelum) |
245 |
| 14 |
Combined
Cycle on Gas |
1,260 |
| 15 |
Thar
Coal |
1800 |
| 16 |
Lakhra
Coal |
450 |
| |
|
|
| |
Total |
15,887 |
REMARKS:
All the above mentioned projects are to be undertaken by WAPDA or
as joint venture with the private sector.
REFERENCES
1. Pakistan Water & Power Development Authority, "Power
System Statistics" Twenty Third Issue, March 1999.
2. Government of Pakistan, "Policy Framework and Package of
Incentives for Private Sector Power Generation Projects in Pakistan",
March 1994.
3.
Government of Pakistan, "Policy Framework and Package of Incentives
for Private Sector Hydel Power Generation Projects in Pakistan",
May 1995.
4. Government of Pakistan, "Policy for New Private Independent
Power Projects", July 1998.
5. TA Study of Asian Development Bank, "A Review of the Independent
Power Policy of the Government of Pakistan", Completion Report,
February 1997.
6. Global Water Partnership, "Draft South Asia - Water Vision
2025" Country Report - Pakistan, 2000.
7. Asian Development Bank - TA, Water Resources Sector Strategy,
"National Water Sector Profile", April 2002.
8. The Private Power Infrastructure Board Website http://www.ppib.gov.pk/power_policy.htm
|