 |
|
|
BASHA
DAM
| KEY
FACTS |
| Dam
Type: |
Zoned
earth-rockfill with central core |
| Location:
|
Chilas
on the River Indus |
| Height: |
200
metres (660 ft.) (above river bed) |
| Length
of crest: |
3,018
feet |
| Reservoir
Area: |
27,700
acres |
| Catchment
Area: |
152,100
km2 |
| Gross
Head: |
145
m (476 feet) |
| Average
Flow: |
1,970
m3/sec (69,600 ft3/sec) |
| Design
Flood Discharge: |
19,300
m3/sec (682,000 cusecs) |
| Total
Storage Capacity: |
9.0
km3 (7.3 MAF) |
| Live
Storage Capacity: |
7.0
km3 (5.7 MAF) |
| Total
Volume of Dam: |
58
million yards3 |
| Total
Volume of Fill: |
44
million m3 |
| Installed
Capacity for Hydropower: |
3,360
MW from 12 units |
| Energy
Generated: |
14.1
GWh |
| Spillway
Type: |
Overflow,
with concrete lined chute, flip bucket and plunge pool |
| Spillway
Gates: |
6
- 16.6 x 20 metres (54.5 x 65.6 ft) |
| |
LOCATION
OF BASHA DAM
The
Basha Dam project site has been identified about 314 km upstream
of Tarbela dam on the River Indus and about 165 km south of Gilgit
City. The development of a high dam at Basha will create significant
storage capacity in the Indus valley between Rakhiot bridge and
Dasu-Sazin gorge. The selected axis is the first suitable site
for the construction of such a dam downstream of the relatively
wide and flat reach of the river dominated by the town of Chilas.
The
dam site is located on a pronounced bend of the Indus River, in
a section with steep rock slopes covered locally with a thin veneer
of talus and acree. At the dam axis, the river is some 160 metres
wide. The maximum depth of the river bed alluvium is 55 metres
near the right bank. The bedrock has high strength, moderately
jointed norite (a form of gabbro) and is suitable as foundation
and embankment material. The material constituting the riverbed
is also compact and has low compressibility. However, its location
requires the laying of long distance transmission lines to connect
the hydel power generated to the national grid.
THE
BASHA DAM PROJECT
The
project will comprise of a 660 feet high zoned earth-rockfill
dam, a chute spillway with a flip bucket and plunge pool, one
low-level and three mid-level outlets, intakes, water conduits
on the right side and an underground powerhouse with an installed
capacity of 3,360 MW. The reservoir created behind the dam would
have a gross capacity of 7.3 MAF and a live storage of 5.7 MAF.
The average generation of hydropower by the project is expected
to be 14.1 GWh.
The
dam is planned in two stages:
Stage
I
Additional
comprehensive technical, financial, social and environmental investigations
and studies were proposed to be carried out to fully assess the
feasibility. This would also facilitate the selection of an appropriate
project layout to develop the hydroelectric potential of the Indus
River at Basha. The activities of this stage are expected to be
completed in 54 months.
Stage
II
The
detailed engineering design of the selected project layout will
be prepared to the level required for tendering purpose in this
stage. Tender documents of all major contracts will also be completed.
This stage will take another 42 months, with the possibility of
overlap of a period of 12 months.
APPRECIATION
OF THE BASHA DAMSITE
Ample
quantities of suitable material for the production of the impervious
fill are available within reasonable distance of the site. The
rockfill, however, will come from necessary excavations from nearby
quarries. The site topography provides significant confinement
of the embankment on both the upstream and downstream toe of the
dam. The dam will be inherently stable and is designed to resist
severe seismic loadings expected in the region. The spillway will
be located on the right bank and will pass maximum floods from
glaciers. A flood caused by a landslide of magnitude equal to
that of 1841 could be passed by making use of a freeboard.
The
four tunnels in the right abutment will be used for river diversion
during the construction period and converted to intermediate and
low-level outlets to meet irrigation needs in the downstream area
when the reservoir level is below the spillway crest.
The
good bedrock favours an underground powerhouse, which will be
located in the left abutment. The transmission facilities will
deliver power generated at Basha to areas of Pakistan showing
generation deficit.
It
is estimated that the life of Basha reservoir will be limited
by sedimentation to about 80 years. In the early years of Basha's
operations, the sediment inflow to Tarbela will be reduced to
40% of the present inflow. As a result, the life of Basha and
Kalabagh (if executed) will be significantly prolonged. The positive
impact on the two reservoirs will be felt for over a century.
RESISTANCE
FROM BY LOCAL PEOPLE
There
has been resistance from the local people from the onset. The
main demands of the local people are:
-
Settlement
of boundary dispute
-
Share
of royalty accrued from the revenue of the project
-
Many
other demands including compensation and employment of local
people
One
major concern of the Northern Areas populace is the location of
the powerhouse on the left side inside NWFP. The Constitution of
Pakistan has given royalty rights to the province where the power
station is located and not the reservoir. This issue caused a major
portion of the social problems.
In
efforts to resolve the disputes, the Government of Pakistan held
4 high level meetings during 1990-92 in the Ministry of Kashmir
Affairs and Northern Areas (KANA) at Islamabad. KANA constituted
a Standing Committee comprising of the NWFP Government and local
civil administration functionaries concerned with the issue on September
12, 1995. The Standing Committee held two meetings in 1995. WAPDA
is also actively pursuing the problem in order to the remove the
bottlenecks.
ENVIRONMENTAL
CONSIDERATIONS
Large
hydroelectric projects have a number of environmental impacts. These
cause major problems that have to be encountered at the time of
project conception. Basha dam was no different in this regard. In
fact, given its location at a high elevation and the tough terrain,
the nature of impacts becomes even more grave:
1.
Resettlement of the local people is an important aspect, which becomes
more serious where individual landholdings are comparatively small
and the cultivable area is scarce due to mountainous terrain.
2. Project construction is bound to affect the natural environment
- both flora and fauna - which is quite dense. Here the construction
activities of the dam, development of roads, quarrying, etc have
to be taken into account. 120 km of the Karakoram Highway (KKH)
is also expected to be submerged. In order to carry heavy equipment
to the dam site through KKH would require improvement in its present
condition.
3. Soil erosion may deteriorate a vast area of land and also induce
instability in downstream irrigation channels due to fluctuations
based on the reservoir level.
4. Altered stream flow and nutrient content including sediments
will cause changes in the habitat.
5. Other downstream effects are likely to impact water supply, fisheries,
navigation, aesthetics and recreation.
6. Dams maintain thermally stratified reservoirs which tend to alter
thermal regimes, reduce dissolved oxygen content, reduce turbidity
and elevate the level of manganese, iron, ammonia-nitrogen and hydrogen
sulphide. There is also tendency for loss of phytoplanktons, which
are the staple diet of a number of fishes and other aquatic life.
7. Basha dam will be located in a seismically sensitive area. There
are certain researches that indicate that the impoundment of water
in the vicinity of faulted area poses a potential impact towards
increasing the earth tremors.
THE
CURRENT STATUS
According
to the plan, the following activities were to be conducted in 1999
-2000 period: surveys/ studies regarding socio-economic status,
consolidation of hydraulic and sedimentation data by ISRIP and consolidation
survey by fixing bench marks and other reference points. Due to
difficulties in accessing the site, resistance from locals and some
other problems, the planned activities could not be carried out.
The
Panel of Experts recommended, in the light of the PC-II performa,
that the planning of the project be in two stages costing Rs. 1,636.28
million including the foreign exchange component (1988 prices).
The financing of 399.2 million in local currency and US$ 25 million
in foreign currency was approved in the year 2000. The budget needs
to be revised for the current timeframe. The total expenditure incurred
up to June 2000 on the Basha dam project was Rs. 83.552 million.
A feasibility
study conducted in the 1980s has now been ranked as a pre-feasibility
study. A 3-year feasibility study is in the final stages of award.
Due to non-availability of foreign exchange and local financing,
an amount of Rs. 900 million has been allocated for the feasibility
of Basha dam of which Rs 300 million will be spent in the year 2001-02
with no foreign exchange component. Other than this amount, the
government has also allocated Rs 360 billion for the construction
of the dam from the year 2006 onwards.
REFERENCES
1.
Montreal Engineering Company, "Basha Storage and Power Project
- Feasibilty Study", Hydroelectric Ranking and Feasibility
Studies for Pakistan - Phase B, October 1984.
2. Montreal Engineering Company, "Inventory and Ranking Study",
Hydroelectric Ranking and Feasibility Studies for Pakistan - Phase
A, November 1984.
3. Pakistan Water & Power Development Authority, "Annual
Report 1999-2000", 2001.
4. Dr. Bashir A Chandio & Ms Nuzhat Yasmin, "Proceedings
of the National Workshop on Water Resources Achievements and Issues
in 20th Century and Challenges for the Next Millennium", Pakistan
Council of Research in Water Resources, June 1999.
5. Centre of Excellence in Water Resources Engineering, Lahore,
"Proceedings - Water for the 21st Century: Demand, Supply,
Development and Socio- Environmental Issues", June 1997.
6. Planning Commission, Govt of Pakistan (Sep 2001), "Ten Year
Perspective elopment Plan 2001-11& Three Year Development Programme
2001-04".
|