|
ALLAI
KHWAR HYDROPOWER PROJECT
| KEY
FACTS |
| Dam
Type: |
Gravity |
| Gross
Head: |
712.5
metres (2,337 ft) |
| Height
of Main Dam: |
107
feet |
| No.
of Units: |
Two |
| Original
Installed Capacity: |
121
MW |
| Energy
Generation Capacity: |
518
million KWh |
| Project
Cost: |
US$
172 million (Price Index 2002) |
| Energy
Generation Cost: |
US$
0.051 |
PROJECT
LOCATION
The
Allai Khwar Hydel Development Project is located on a left bank
tributary of the River Indus in the northern mountainous region
of Pakistan. The project site is near Besham, a town located on
the Karakoram Highway in the north of Mansehra District. The project
site is not easily accessible all round the year, particularly during
harsh seasons.
VARIATIONS
DUE TO ENVIRONMENTAL CONSTRAINTS
GTZ
/ SHYDO prepared an inventory study between 1987-91 of the hydropower
potential of a number of projects in various NWFP districts. At
that time, the proposed development of the Allai Khwar catchment
included a flow diversion from the adjacent Kuz Khwar to Allai Khwar.
Kuz Khwar is one of the two main tributaries of the Chor Nala, which
joins the Indus upstream of the Allai Khwar confluence with the
river.
Following
an Environmental Assessment Report and discussions between the Government
of NWFP and KfW in June 1996, a decision was taken to abandon the
original concept due to a dispute over land ownership in the Kuz
valley between the peoples of the Kohistan and Allai areas.
Consequently,
a draft conceptual report was prepared covering the Allai catchment
only. This was completed in October 1996. The report explicated
the study and evaluation of hydropower development possibilities
within the Allai Khwar catchment. Special emphasis was given to
an attractive scheme between a dam site on the Allai Khwar near
the village of Telus and a powerhouse site on the left bank of the
Indus, which could give a head up to 700 metres.
This
was followed by a Feasibility Study by Lahmeyer International that
was overseen by an independent panel of experts. The results of
the environmental and social studies imposed certain constraints
related to the submergence of the Telus village, as this was fraught
with risk and socially unacceptable. Consequently, a run-of-the-river
scheme with a small reservoir allowing daily power peaking was recommended.
PROJECT
OVERVIEW
The
Allai Khwar Hydroelectric Project will be a stand-alone initiative
built by diverting the Allai Khwar flow to the Indus through a narrow
ridge separating the rivers. The waterways length would be in the
order of 3 - 3.6 km which would result in a favorable ratio between
the waterways and the head. The project is also considered attractive
due to its peaking power plant that would provide sufficient daily
pondage volume. This means that better monthly/ seasonal storage
could be provided.
The
village of Telus and its facilities are located within the reservoir
areas. Inundation of Telus and/ or its facilities may create substantial
difficulties in project implementation if dam heights are exceeded
beyond certain limits.
ALTERNATIVES
CONSIDERED
Initially
five alternatives were considered for project construction. After
the initial studies, two of them were excluded from further examination
due to constraints related to geological storage and environment.
The
three remaining alternatives were then studied in detail. The Run-of-River
Option was considered acceptable but a model-testing study was required
before the feasibility to ascertain satisfactory operation of the
reservoir. The two other alternatives were at the same height but
their full supply levels were at 1280 and 1255 metres above sea
level (masl) respectively. A survey by Global Positioning System
(GPS) found that Telus was located at an elevation of 1262 masl.
The findings left only two feasible options for the project i.e.
Run-of-River and at 1255 masl.
The
option finally selected was run-of-the-river at a dam height of
712.5 metres, with full supply level of 1255 masl that had a catchment
area of 302 km2 and discharge of 13.9 m3/s. The height of the dam
was 150 metres and storage was 31.9 million m3.
CURRENT
STATUS
Sarhad
Hydel Development Organization (SHYDO) completed the Feasibility
Study of the Allai Khwar Hydropower Project with an installed
capacity of 163 MW. KfW financed the study. Recently, the
Ministry of Water and Power has directed SHYDO/ GTZ to optimize
the plant capacity at about 121 MW.The PC-II for detailed
engineering procedures and preparation of tender documents
amounting to Rs 36.484 million with foreign exchange equivalent
to Rs. 9.4 million has been approved. |
 |
| International
contractors have been short-listed for equipment. Moreover,
the PC-1 has also been submitted to the Ministry of Water and
Power. Construction of model is underway in Nandipur and testing
will be started shortly.The government has also allocated Rs.
6.71 billion for the construction and supervision of the Allai
Khwar project in the Ten Year Perspective Plan covering the
period 2001-06. |
1.
Sarhad Hydel Development Organization - NWFP, "Allai Khwar
Hydel Development Scheme Selection for Feasibilty - Steering Committee
Meeting", Working Paper, May 1997.
2. Lahmeyer International and Knight Piesold, "Allai Khwar
Hydel Development - Conceptual Study", for SHYDO, October 1996.
3. Lahmeyer International and Knight Piesold, "Allai Khwar
Hydel Development - Inception Report", September 1995.
4. Sarhad Hydel Development Organization - NWFP, "Allai-IV
Hydropower Project", Briefing Note, 1994.
5. Pakistan Water & Power Development Authority, "Annual
Report 1999-2000", 2001.
6. Pakistan Water & Power Development Authority, "Monthly
Progress Report for February 2002", Hydroelectric Planning
Organization, March 2002.
7. Planning Commission, Govt of Pakistan (Sep 2001), "Ten Year
Perspective Development Plan 2001-11& Three Year Development
Programme 2001-04".
|