|
Environmental impact
of Chashma Barrage
By Saeed Akhtar Niazi
Wapda may certainly boast of a fairly creditable record in
meeting environmental standard. Exceptions, however, prove
the rule. This exception is the Chashma Barrage Project located
on river Indus in district Mianwali.
Built between 1967 to 1971, it is one of
the many major engineering works that form part of Indus basin
Treaty of 1960 between India and Pakistan.
From the environmental point of view, this
project was far from ideal. The barrage, with its pond level
at 649 SPD, submerged 137 sq miles (355 sq km) of beautiful
farmland. The affected area is far in excess because of land
acquisition up to 650 SPD. According to project reports, 29
(in fact, 34) villages) were displaced with a population of
22400 people (in fact, far more) in mid 60’s. Various
aspects of the adverse environmental impact are discussed
below.
The fact that the barrage was located in
plain area, it inundated a very large fertile land that was
a granary for the entire district. There used to be abundance
of livestock, supply of dairy and poultry products was plentiful.
The number of persons displaced was high and in tribal setting,
the displacement amounted to amputation of an arm of the tribe,
inhabiting the area. There were other damages that unfolded
after the commissioning of the barrage.
The ever-changing lake level provided an
ideal location for the mosquitoes to breed. This resulted
in making the life miserable for the population dwelling along
the lake. It is literally impossible for the people to sleep
in the open in sweltering summer months. They have to readjust
their entire life style with limited relief. During pollen
period, air gets studied with spores which cause allergic
reactions like sneezing, asthma, bronchitis etc. Life is equally
hard for livestock.
The warble fly is found in plenty. It lays
eggs at certain locations on the body of the cattle perforating
the skin with fatal consequences. The vast wasteland difficult
to normal access, provide sanctuary to outlaws and bandits.
Kidnapping for ransom at one time became frequent. Above all,
it provides a conduit for traffic of arms and narcotics.
The original owners of the land having been
displaced and lately, professional bandits thinning out, the
area has entered yet another era. It is now free-for-all.
It is getting converted into a sort of ‘micro fiefdoms’.
Its role as a source of food grain and livestock seems to
be returning but still remaining a lawless area.
During pre-barrage period when the wetland
was inhabited, there were a large number of trees. After the
formation of the lake, trees disappeared.
The most important aspect of any development
of the like nature where large-sale displacement is involved
is that the resettlement gets the top priority. Affected persons
after leaving their hearths and homes, expect to get a fair
deal.
Uprooting people and throwing them out in
wilderness of the Thal desert, in state land already in unauthorized
occupation of the local people and without providing the promised
infrastructure, is height of injustice to the affected people.
Many of the displaced persons are facing
long drawn litigations, reportedly several hundreds in number,
till now, after this displacement and supposed resettlement.
Struggle for survival of these families continues after 35
years.
The downstream of the barrage suffered even
bigger disaster. he barrage has been located on the left bank.
This has drastically changed the historic course of the river,
shifting the mainstream to the left bank. Thousand of acres
of well cultivated wetland has been destroyed. The ancient
towns on the left bank highlands aree seriously affected.
To name only the bigger and historic towns along the 99 ft.
wide historic Sher Shah Soori road, downstream of he barrage
upto Kalurkot, a stretch of 60 km are, Alloali, Doaba, Moosiwala,
Piplan, Kalurkot. Nobody cared to construct guide works and
spurs to prevent the onslaught of the river that later caused
destruction.
As a result, town of Tiba Mehrban Shah including
its railway station went completely out of existence. Sixteen
km of railway track that was washed away, had to be relocated.
Hurriedly constructed remedial works at a later stage are
hardly enough to control the havoc that the river plays year
after year.
The government of Punjab and Flood Commission
of Pakistan has belatedly constructed guide works and spurs
but such works are not quite satisfactory to withstand the
onslaught of the rivers in spate. More spurs are believed
to be under consideration for construction in due course.
It is only to be hoped that further works are properly planned,
designed and robustly constructed to perform the required
function.
Another serious issue that has cropped up
after the construction of the barrage is the disposal of sewerage
into the lake. Waste of more than 2,50.000 humans is dumped
directly into the lake by indiscreet municipal authorities
who have not cared to treat it before disposal. Impact of
this might have perhaps been somewhat less if it was still
running river rather than an oft fluctuating lake. Environmental
monitoring could bring out this glaring source of environmental
degradation and tell the concerned authorities to see, sense
and take appropriate steps.
Development works including the construction
of dams and barrages must continue as and where needed in
the national interest. However, only those projects, which
are environmentally benign or those which significantly enhance
the lifestyle of the affected persons, should be preferred.
National and international environmental standards must be
met not only in theory and as a lip service but in practice.
The periodic inspections of the engineering
works by the project authorities must include inspection and
report on environmental issues. The inspection team may include
experts from national environment organization or their approved
consultant. The project environmental directorate should remain
in existence long after, to monitor any adverse impact after
the commissioning of the project. The owner must remain committed
to fund any remedial works that may be identified and required
in due course.
Chashma barrage is delivering the benefits
expected out of it. It still has a much needed live storage
of 0.3 maf. C-J Link canal is serving the desired purpose.
It continues to divert Indus waters to Jhelum. It shall feed
Greater Thal Flood Canal in due course. The right bank high
level irrigation canal is also serving the desired objective.
The benefits of Chashma have considerably increased by the
addition of 184 MW hydro electric power plant. It is only
regrettable that it was not built according to its optimized
capacity of 285 MW.
Chashma project however, suffers from multifarious
deficiencies on the environmental side. The permanent damages
are irretrievable. Further damages and some impacts of non-permanent
in nature can be redressed or at least mitigated. For this
end in view, the following suggestions are offered by way
of illustration, for the eyes and ears of experts.
i) The environmental component of Chashma
project must be revisited. The review team should include
environmental experts if not for a lead role, at least as
important members of the group. It should identify the deficiencies
and prepare action plan to remove these. Realistic cost estimates
should be prepared and funds arranged. Wapda should bear the
major brunt as it defaulted in the first instance. Moreover,
it has now the benefit of a continuous cash stream from its
hydroelectric project.
ii) Resettlement issue be reopened and it
should be ensured that the displaced persons get the facilities
promised and committed at the time of eviction e.g. hospitals,
schools and organized townships. As a matter of fact, the
facilities might be upgraded to meet the current standards.
iii) A bridge should be built across the
lake (river Indus) so as to make the lake area more accessible.
This will greatly help in establishing rule of law, particularly,
to interrupt and mitigate the arms and drug trafficking.
iv) Leasing or auctioning of the land in
the lake area should be done in an orderly and organized manner
in consultation with the political leadership of the districts
involved.
v) A comprehensive plan should be prepared
to rein in the river to prevent its onslaught on the towns
in the reach between the barrage to the town of Kalorkot and
beyond if necessary.
vi) Identification of damages should be
carried out in C.J. Link and Chashma right bank canal area
and remedial actions taken as and where necessary.
vii) National environmental agency
should take notice of the disposal of human waste into the
lake and issue suitable directive to the concerned municipal
authorities to take steps to provide sewerage treatment plants
before disposing of waste into the lake.
http://www.dawn.com/2005/06/20/ebr9.htm
|