The single renewable
energy resource that Pakistan possesses in abundance
is hydropower, the most environmental friendly, cheapest
source of energy. It has a potential of more than 41,722MW.
Despite this, Pakistan now is faced with a most serious
energy shortfall. The acute shortage of electricity
has resulted in loadshedding during the current summer
season, costing the economy millions of rupees.
The installed power generation capacity at the end
of 2005 was19,560MW, of which 65 per cent was thermal,
33 per cent was hydroelectric and 2.4 per cent was
nuclear. The 33 per cent share of hydroelectric power
amounts to only 6,595MW. We should not forget the
fact that the projected lifetime of the existing natural
gas and oil is just over 15 and nine years respectively.
Domestic coal reserves may be exploited only at great
financial and environmental costs. Seventy per cent
of Pakistan's oil needs are met through imports. The
average cost of hydel energy generation in Pakistan
was Rs0.50 per kilowatt hour in 2000-01. The annual
per capita electricity consumption in Pakistan is
around 320kwh, and this only caters for 60 per cent
of the population. Forty per cent of Pakistanis still
have no access to electricity. In view of these facts,
the best solution to Pakistan's energy/electricity
crisis is hydropower. An abundant, cheap, environmental
friendly and renewable source of energy has remained
untapped.
To meet Pakistan's power requirement, WAPDA and the
Ministry of Water and Power developed a strategy called
the Hydropower Development Vision-2025 in the year
2001. The strategy was based on an average annual
demand increase of 3.7 per cent. Recently though the
demand for electricity rose sharply, in excess of
eight per cent per annum during the last two years.
In Vision-2025 a short-term plan was developed and
the commissioning date of eight hydel projects with
a total generation capacity of 716MW was fixed on
June 2006. These projects were proposed and designed
as 'run-of-river' plants, meaning one with little
or no storage capacity, such as Ghazi Barotha hydropower
project, in which no big reservoir is to be constructed.
But unfortunately none of these projects could be
completed. The root-cause of the failure to provide
the needed energy is lack of strategy for implementation.
The strategy prepared by the ministry fails to take
into account the ground realties and the project management
capabilities of executing agencies.
The World Bank rightly proposed institutional reform
in WAPDA for decentralisation in order to increase
efficiency in management. While preparing the future
strategy the Ministry of Water and Power should keep
in view the completed hydropower projects, such as
Ghazi Barotha, and the lessons learnt from them. The
Ghazi Barotha project's feasibility survey was carried
out in 1987 and the project finally commissioned on
19 August 2003. This means that 16 years are required
for WAPDA to complete a run-of-the-river project.
Another cause of the present energy crisis is that
the federal government has not taken small hydropower
projects (SHPs) in its own hands. Such projects are
very viable as they do not require building of large
dams and do not pose problems of deforestation, submergence
or rehabilitation. Comparatively small capital investment
and short gestation periods are required to complete
these projects and they cause minimal transmission
losses occur compared to WAPDA's current line losses,
which are more the 25 per cent.
In Pakistan all small hydropower projects up to 50MW
are the responsibility of the provincial governments
which cannot construct small hydropower projects due
to financial constrains, among other reasons. In India,
developing small hydro projects at a fast pace is
one of the components of their energy policy. The
central government there has completed 90 small hydro
projects with 270MW capacity in the past five years.
The state of affairs in Pakistan should change. Punjab
has enough financial resources but it has made no
real progress on small hydropower plants even though
WAPDA has not only identified various locations having
a potential of 350MW but also completed the necessary
design works. In Azad Jammu and Kashmir, which is
endowed with abundant hydel potential, the AJK Hydroelectric
Board has only completed hydro projects having a capacity
of 36MW against an identified potential of 5,329MW.
This hydrogenation cannot even meet the electric demand
of AJK itself, which is 250MW; while the anticipated
power demand by 2007 will be 350MW. The AJK Hydroelectric
Board is facing serious financial problem in starting
the projects as funding is not available. International
donor agencies are reluctant. In the Indian-held Kashmir,
recently twenty small hydro projects were commissioned
at various selected sites by the UNDP. Baglihar and
Kishan Ganga hydropower projects are in the stage
of completion.
The biggest problem is faced by our Northern Areas
where the electricity demand is more then 100MW but
total power generation from hydel power stations is
a mere 46MW. To bridge the gap between demand and
supply a diesel power plant with a total generation
of 5MW has been commissioned by the government. Instead
of tapping ingenious hydropower potential, the Ministry
of Water and Power has decided to construct a 765-kv
transmission line that is 794-km-long, to import 1000MW
from Tajikistan via Afghanistan at a much higher rate.
For self-reliance in energy and for eradicating poverty,
hydropower is recognised as a renewable source which
is economical, non-polluting and environmentally benign.
In order to maintain a balance between hydropower
and thermal power, the ministry should announce a
policy to accelerate hydropower generation in the
country. Development of small hydro projects at an
accelerated pace should be one of the tasks set by
the policy to meet the present power crisis. This
is the only cost-effective solution to meet the increasing
electricity demand.
Success here is possible only if public-sector funding
is made available by the government. The financing
of such projects remains a problem for funds from
international donors for such projects are difficult
to get, considering their commitment to facilitate
investments in private thermal-based power plants.
Instead of trying to imitate and compete with India
in nuclear energy, we should consider the way countries
like Laos, Thailand and China have developed small
hydropower projects for development and economic prosperity.
The writer is a visiting research fellow at the Sustainable
Development Policy Institute in Islamabad. Email:
abbasi @sdpi.org